Dart Energy Storage A1
50 MW storage in Taylor, TX · In queue since February 2025 · Proposed COD November 2028
50 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-30
Projected COD moved
0 times
Nov 2028 → Nov 2028
Net change
0 months
first report to latest
Capacity
50 MW
unchanged in the reports
Latest stage
Screening started
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Dart Energy Storage A1 is a proposed 50 MW battery energy storage development project located in Taylor County, Texas. The project is being developed by Dart Energy Storage LLC and consists of a single battery storage component with a capacity of 50 MW. It is designed to connect to the grid via a tap on the 138 kV line between the Abilene Maple Street substation (#6290) and the Abilene East substation (#6275).
The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID 28INR0293 and entered the queue on February 25, 2025. Its interconnection agreement process is at the Facility Study stage, and the project has a proposed commercial operation date of November 30, 2028. The project's current queue status is listed as suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Taylor
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Dart Energy Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP138KV #6290 ABILENE MAPLE STREET - #6275 ABILENE EAST
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.