2 Cedar Wind
180 MW generation in Fannin, TX · In queue since July 2025 · Proposed COD May 2028
180 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-02
Projected COD moved
0 times
May 2028 → May 2028
Net change
0 months
first report to latest
Capacity
180 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT interconnection queue entry submitted
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of May 2028. No independent news or press releases found to validate or contradict this date.
Developer: Only LBNL filing identifies developer as 'SunWR, LLC'. No public information found about this entity, its parent company, or whether it's a project-specific LLC or operating company.
Status: LBNL status shows 'active' with recent queue date (July 2025). No news coverage or press releases found to provide additional status context.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
2 Cedar Wind is a proposed 180 MW wind generation project in Fannin County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The development project is being pursued by SunWR, LLC and would use wind turbine technology to generate electricity. It is planned to connect to the grid at a tap on the 345 kV line between the Valley South substation (1729) and the Anna Switch (2373).
The project entered the ERCOT interconnection queue on July 7, 2025, under queue identifier ERCOT-28INR0286, and its queue status is listed as active. Its proposed commercial operation date is May 2, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fannin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SunWR, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1729 Valley South – Anna Switch 2373
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- PLATINUM_RN
- POI Substation
- Valley South Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.