Mojo Solar
527.94 MW hybrid in Wilson, TX · In queue since March 2025 · Proposed COD June 2028
527.94 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
0 times
Jun 2028 → Jun 2028
Net change
0 months
first report to latest
Capacity
528 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-28inr0250-mojo-solar
- ercotqueue.com/project/28INR0250
- interconnection.fyi/project/ercot-28inr0250
- cleanview.co/power-projects/planned/solar-farms/texas/28INR0250/mojo-solar
- facebook.com/groups/wilsoncountyrpp/posts/1008850245013189/
Commercial operation date: Only queue-derived data exists. Infrasure restates the 'proposed commercial operation date is June 30, 2028' and Cleanview says 'Expected online 2028'. Both appear to mirror the queue filing, so there is no independent developer or press-release COD.
Developer: Power Synergy appears in the LBNL filing and in aggregator pages (ercotqueue.com, infrasure.ai), which likely copy the queue data. No press release or parent-company information was found. A Facebook group post links the Mojo Solar site to a 'Misae Energy Hub', but it is an unverified local comment and is not used to change the developer.
Status: LBNL and several aggregators (interconnection.fyi, infrasure.ai, ercotqueue.com) list the project as active with no IA. The interxdata.com 'operational' label conflicts with the Facility Study stage and the 2028 target COD, so it is treated as a data error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Mojo Solar is a proposed 527.94 MW solar photovoltaic generation project in Wilson County, Texas. The project, developed by Power Synergy, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0250, with a queue entry date of March 3, 2025. The proposed commercial operation date is June 30, 2028.
The project is planned to interconnect at the Tap 345 kV 5133 Elm Creek - 5901 San Miguel CKT 1 & 2. Mojo Solar has been mentioned in recent industry news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Power Synergy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 5133 Elm Creek - 5901 San Miguel CKT 1 & 2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Elm Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.