Copperleaf Energy Storage (ERCOT-28INR0118) — Project Summary

Queue ID
ERCOT-28INR0118
Capacity
306.53 MW
Technology
Battery
Status
active
Location
Wichita, TX
Region
ERCOT
Developer
Copperleaf Energy Storage, LLC
IA Status
Facility Study

Copperleaf Energy Storage

ERCOT-28INR0118BetaActiveBatteryERCOTLBNL + Live

306.53 MW storage in Wichita, TX · In queue since November 2024 · Proposed COD September 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

306.53 MW

Capacity

1

Components

Battery

2 years

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 10m

Facilities Study50%
Queue EntryNov 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-25

Queue history
28INR0118 · 23 monthly ERCOT reports, Nov 2024 – Sep 2026

Projected COD moved

2 times

Dec 2028 → Sep 2029

Net change

+9 months

first report to latest

Capacity

167 → 306 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 19, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Sep 25, 2029
From queue filing
Developer in saved assessment
Copperleaf Energy Storage, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study phase with no interconnection agreement executed. ercotqueue.com lists a 1% build-chance, and no construction or financing news was found.
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. infrasure.ai/project/ercot-28inr0118-copperleaf-energy-storage
  2. ercotqueue.com/project/28INR0118
  3. interconnection.fyi/project/ercot-28inr0118
  4. cleanview.co/power-projects/planned/battery-storage-projects/texas/28INR0118/copperleaf-energy-storage
  5. ercotqueue.com/developer/copperleaf-energy-storage-llc
  6. bizapedia.com/tx/copperleaf-energy-storage-llc.html

Commercial operation date: No developer press release or news gives an independent COD. Aggregators (Infrasure: 'Proposed COD: 2029-04-18'; Cleanview: 'Expected online 2029') appear to be derived from the same queue data and differ from LBNL by under a year, so the LBNL date is retained.

Developer: Every source, including ercotqueue.com and Infrasure, names Copperleaf Energy Storage, LLC as developer. Corporate registry listings show a Texas foreign LLC registered in April 2024 (Austin address). No parent or operating company is identified publicly.

Status: LBNL and the tracker sites (interconnection.fyi, ercotqueue.com, Infrasure) all list the project as active. A Facebook snippet about ERCOT cancellations mentions a separate 'Copperleaf Energy Storage Increase' entry (28INR0220), which is a capacity-increase request, not a withdrawal of this project.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Copperleaf Energy Storage is a proposed 167.2 MW battery storage project located in Wichita County, Texas. The project, developed by Copperleaf Energy Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0118, with a queue entry date of November 19, 2024. Its proposed commercial operation date is April 18, 2029, and its interconnection agreement status is currently in the Facility Study phase.

The proposed project consists entirely of battery storage, with a total capacity of 167.2 MW. The point of interconnection is at the 1426 FISHER ROAD SWITCH 138 kV location. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wichita

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Copperleaf Energy Storage, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV Fisher Road Switch (#1425) – Riley (#6101)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.