Biggs BESS
200 MW generation in Mcculloch, TX · In queue since July 2024 · Proposed COD June 2029
200 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-16
Projected COD moved
1 time
Nov 2028 → Jun 2029
Net change
+7 months
first report to latest
Capacity
200 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of November 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity 'Biggs Battery Facility, LLC' is known. No press releases or corporate announcements found to identify a parent operating company or confirm this is a project-specific LLC.
Status: LBNL shows Active status with Facility Study phase initiated in July 2024. No news coverage found to indicate construction activity, financing, or status changes.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Biggs BESS (queue ID ERCOT-28INR0110) is a proposed energy storage development project in McCulloch County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Biggs Battery Facility, LLC and has a total proposed capacity of 200 MW. Although its queue record classifies the technology as Solar+Battery, the only component listed is a 200 MW battery energy storage system, and no solar capacity is specified. The project is categorized as a generation project and would connect to the grid at the 76006 Bow Wood 345 kV point of interconnection.
The project entered the ERCOT interconnection queue on July 22, 2024, and its queue status is listed as active. It is in the Facility Study phase of the interconnection process, meaning an interconnection agreement has not yet been executed. The proposed commercial operation date is June 16, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mcculloch
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Biggs Battery Facility, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76006 Bow Wood 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Bow Wood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.