Mirando Valley Wind
478.74 MW generation in Jim Hogg, TX · In queue since August 2024 · Proposed COD July 2028
478.74 MW
Capacity
1
Components
Wind
2y 3m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-06
Projected COD moved
0 times
Jul 2028 → Jul 2028
Net change
0 months
first report to latest
Capacity
351 → 479 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-28inr0072-mirando-valley-wind
- ercotqueue.com/project/28INR0072
- interconnection.fyi/project/ercot-28inr0072
- ercotqueue.com/developer/ace-devco
- quicksandcheck.com/texas/jim-hogg-county/
- cleanview.co/power-projects/planned/wind-farms/texas/28INR0072/mirando-valley-wind
Commercial operation date: Every source that gives a COD (infrasure.ai, interconnection.fyi, Quicksand Check, Cleanview) repeats the queue's July 2028 proposed COD, and none is independent of it. No press release or news item gives a financing-backed date, so the LBNL date stands.
Developer: ERCOT-derived aggregators (ercotqueue.com, interconnection.fyi, infrasure.ai) all name ACE DevCo NC LLC. No source identifies a parent or operating company behind it, so I could not resolve whether it is a shell. The 2008 Texas LLC 'Mirando Valley Wind Energy, L.L.C.' and the old PUC filing are not clearly tied to this project, so I did not use them.
Status: LBNL and the aggregators agree the project is active and not operational. No evidence of construction, withdrawal or suspension was found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Mirando Valley Wind project is a proposed 351 MW wind generation facility in Jim Hogg County, Texas. The project, being developed by ACE DevCo NC LLC, is located within the ERCOT region and interconnected to the grid at Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1.
The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0072, with a queue entry date of August 16, 2024. Its proposed commercial operation date is July 6, 2028, and its interconnection agreement status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jim Hogg
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ACE DevCo NC LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80220 Cenizo - 80079 Cruce Ckt-1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cenizo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.