Sitges Wind
600 MW generation in Motley, TX · In queue since March 2024 · Proposed COD March 2030
600 MW
Capacity
1
Components
Wind
2y 8m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
6 years
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-31
Projected COD moved
1 time
Jan 2029 → Mar 2030
Net change
+14 months
first report to latest
Capacity
251 → 600 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-28inr0017-sitges-wind
- interconnection.fyi/project/ercot-28inr0017
- ercotqueue.com/project/28INR0017
- app.nrgmap.com/queues/ercot-28inr0017
- cleanview.co/power-projects/planned/wind-farms/texas/28INR0017/sitges-wind
- quicksandcheck.com/texas/motley-county/
Commercial operation date: No news or press-release signal gives a different date. Queue aggregators (infrasure.ai, interconnection.fyi, cleanview.co) repeat the LBNL/ERCOT proposed COD of 2030-03-31, so they are not independent confirmation. The one outlier, an infrasure.ai list showing 2029, is unexplained.
Developer: The LBNL filing entity, NextEra Energy Interconnection Holdings, LLC, is a NextEra-affiliated interconnection vehicle. ercotqueue.com and interconnection.fyi also list Whistling Flats Wind, LLC as the project owner or developer, which looks like a project-level LLC. No press release names the operating company, so NextEra Energy Resources as the parent is an inference.
Status: LBNL lists the project as active, and NRG Map (as of Sept 2026) and interconnection.fyi confirm it. ercotqueue.com shows no IA and a 10% build chance. interxdata's 'operational' label conflicts with every other source and is likely a data error. The related Sitges Wind 2 (29INR0112) is withdrawn, but that is a separate queue entry.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Sitges Wind is a proposed 300 MW wind generation project located in Motley County, Texas. The developer is NextEra Energy Interconnection Holdings, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0017, with a queue entry date of March 22, 2024.
The proposed commercial operation date for Sitges Wind is March 31, 2030. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 59904 Cottonwood to 23922 White River Ckt 2.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Motley
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
NextEra Energy Interconnection Holdings, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 59904 Cottonwood–60500 Edith Clarke
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Max 4 Wind
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.