Draco Solar
500 MW generation in Borden, TX · In queue since April 2025 · Proposed COD August 2027
500 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-19
Projected COD moved
0 times
Aug 2027 → Aug 2027
Net change
0 months
first report to latest
Capacity
500 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-27inr0499
- infrasure.ai/project/ercot-27inr0499-draco-solar
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0499/draco-solar
Commercial operation date: Only the LBNL/ERCOT filing gives a COD for this Borden County project (proposed 2027-08-19). Aggregators such as interconnection.fyi, infrasure.ai and cleanview repeat that date and add no independent signal. No developer press release or news item for the Texas project was found.
Developer: Only the LBNL filing entity (Draco Solar LLC) is available, and no parent or operating company was identified for the Texas project. The news-extracted 'Southern Power' developer belongs to the Lamesa Solar Facility, which reached COD in 2017, so it was discarded as a mismatch. The Brazilian Draco Solar Complex (Atlas Renewable Energy) is also a different project.
Status: LBNL lists the project as active, not operational, with IA status 'Facility Study' and no IA date. interxdata's 'operational' label conflicts with LBNL and the other aggregators, and the Lamesa 'online' data belongs to a different project, so neither was used.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Draco Solar project is a proposed 500 MW solar generation facility in Borden County, Texas. Developed by Draco Solar LLC, the project is interconnected within the ERCOT region and has appeared in recent industry news.
The project entered the ERCOT interconnection queue as entry ERCOT-27INR0499 on April 21, 2025, with a proposed commercial operation date of August 19, 2027. The point of interconnection is Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Borden
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Draco Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Long Draw (59900) – Faraday (59905) CKT 1 and LONGDRAW (59900) - GALVANI(59912) CKT 2
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.