Moon Chapel Wind
379.2 MW generation in Tom Green, TX · In queue since February 2025 · Proposed COD October 2028
379.2 MW
Capacity
1
Components
Wind
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
Entered ERCOT interconnection queue, Facility Study phase
Proposed commercial operation date per LBNL queue filing
The Moon Chapel Wind project is a proposed 379.2 MW wind generation facility in Tom Green County, Texas. Developed by Orsted Onshore Development North America, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0445, with a queue entry date of February 14, 2025. The proposed commercial operation date is October 1, 2028.
Recent news coverage has discussed the Moon Chapel Wind project, with articles categorized under hazards and industry.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Orsted Onshore Development North America, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76090 Divide - 76009 Twin Buttes Ckt 1
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CALLAHA_WND1
- POI Substation
- Callahan Divide Wind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.