Bluebonnet Trail Solar
150.9 MW generation in Ellis, TX · In queue since December 2024 · Proposed COD September 2028
150.9 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-19
Projected COD moved
1 time
Dec 2027 → Sep 2028
Net change
+9 months
first report to latest
Capacity
151 → 151 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company. Entity name follows project-LLC naming convention but no parent company identified.
Status: LBNL status shows Active with Facility Study in progress. No public announcements found regarding project advancement, permitting, or construction plans.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bluebonnet Trail Solar is a proposed 150.7 MW solar generation project located in Ellis County, Texas. The project, developed by Bluebonnet trail solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0417, with a queue entry date of December 19, 2024. The proposed commercial operation date is September 19, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for Bluebonnet Trail Solar is Tap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ellis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bluebonnet trail solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.