Cernan BESS
301.15 MW storage in Wharton, TX · In queue since February 2025 · Proposed COD October 2028
301.15 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-02
Projected COD moved
3 times
Dec 2026 → Oct 2028
Net change
+22 months
first report to latest
Capacity
301 → 10 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
- —·Scarlet BESS LLC→Cernan BESS, LLC (name change; no change of parent identified)interchange.puc.texas.gov
Milestones in this assessment
CenterPoint filed the ERCOT SGIA with Scarlet BESS LLC for Cernan BESS at the Texas PUC. Infrasure gives an IA date of 2025-12-30.
interchange.puc.texas.govResearch sources and reasoning (5 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0392/cernan-bess
- infrasure.ai/project/ercot-27inr0392-cernan-bess
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2360
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2519
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&FilingParty=centerpoint&DocumentType=ALL&SortBy=FileStamp&SortOrder=Descending
Commercial operation date: No developer press release or financing-backed target exists. Cleanview repeats the October 2028 date, which matches LBNL. Infrasure shows a proposed COD of 2027-06-01, but it is a single aggregator signal that conflicts with the other two and is not strong enough to override LBNL.
Developer: Texas PUC filings from 2026 identify the interconnection customer as 'Cernan BESS, LLC (f/k/a Scarlet BESS, LLC)', so the LBNL entity has been renamed. No parent or sponsor is publicly named; the LinkedIn snippet mentions the project but not the company.
Status: Primary PUC filings show an executed ERCOT Standard Generation Interconnection Agreement and a later amendment, which means the LBNL 'Facility Study' stage is out of date. The project is not withdrawn and remains listed as active.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Cernan BESS project is a proposed 10.04 MW hybrid battery energy storage system located in Wharton County, Texas. The project, developed by Scarlet BESS LLC, is interconnected within the ERCOT region under queue ID ERCOT-27INR0392. It entered the interconnection queue on February 14, 2025, and has a proposed commercial operation date of June 1, 2027. The interconnection agreement (IA) date is December 30, 2025.
The point of interconnection (POI) for the Cernan BESS project is the Hillje 345kV substation (#44200). The project is classified as a hybrid due to its battery energy storage technology. The project has appeared in recent news coverage regarding energy storage projects in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Scarlet BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Hillje 345kV (#44200)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Cernan BESS Battery Storage in Tennessee queue pipeline — 1 projects by technology and status
Data-driven briefing on Cernan BESS — fleet, generation, financial, and news signals.
Cernan BESS
Data-driven briefing on Cernan BESS — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.