Straight Spur Storage (ERCOT-27INR0386) — Project Summary

Queue ID
ERCOT-27INR0386
Capacity
306.2 MW
Technology
Solar+Battery
Status
active
Location
Andrews, TX
Region
ERCOT
Developer
ENGIE IR Holdings LLC
IA Status
Facility Study

Straight Spur Storage

ERCOT-27INR0386BetaActiveBatteryBatteryERCOTLBNL + Live

306.2 MW generation in Andrews, TX · In queue since November 2024 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

306.2 MW

Capacity

1

Components

Battery

2 years

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 5m

Facilities Study50%
Queue EntryNov 19, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-01

Queue history
27INR0386 · 23 monthly ERCOT reports, Nov 2024 – Sep 2026

Projected COD moved

1 time

Dec 2027 → Apr 2029

Net change

+16 months

first report to latest

Capacity

306 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 19, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 1, 2029
From queue filing
Developer in saved assessment
ENGIE North America
Filed as ENGIE IR Holdings LLC
Status at research time
Active
Active in the ERCOT queue. The screening study is complete and the facility study has started, with no interconnection agreement executed. ercotqueue.com gives it a 1% build chance.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. app.nrgmap.com/queues/ercot-27inr0386
  2. interconnection.fyi/project/ercot-27inr0386
  3. ercotqueue.com/project/27INR0386
  4. ercotqueue.com/developer/engie-ir-holdings-llc
  5. infrasure.ai/project/ercot-27inr0386-straight-spur-storage

Commercial operation date: Every source, including NRG Map ("Proposed online 2029-04-01") and interconnection.fyi, repeats the same ERCOT queue date. These are mirrors of the queue data, not independent developer or press signals, so no newer COD exists to override LBNL.

Developer: The filing entity is ENGIE IR Holdings LLC. ercotqueue.com groups it with ENGIE and ENGIE North America filings under one developer, which suggests ENGIE North America is the operating parent. No press release confirms this, so it is partly inferred.

Status: ERCOT status data as of 2026-09-01 (via NRG Map) shows the project active at "SS Completed, FIS Started, No IA". One aggregator (interxdata) lists it as "operational", which contradicts the ERCOT data and every other source, so I disregarded it.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Straight Spur Storage is a proposed 306.2 MW battery storage project located in Ector County, Texas. The project, being developed by ENGIE IR Holdings LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0386, with a queue entry date of November 19, 2024. The proposed commercial operation date is April 1, 2029.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV ClearFork (Bus # 23876) to Gardenale Switch (Bus # 11157). The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Andrews

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ENGIE IR Holdings LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV ClearFork( Bus # 23876) to Gardenale Switch (Bus # 11157)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.