Comanche BESS (ERCOT-27INR0365) — Project Summary

Queue ID
ERCOT-27INR0365
Capacity
614.4 MW
Technology
Battery
Status
active
Location
Comanche, TX
Region
ERCOT
Developer
ENERGOS BESS
IA Status
Facility Study

Comanche BESS

ERCOT-27INR0365BetaActiveBatteryERCOTLBNL + Live

614.4 MW storage in Comanche, TX · In queue since December 2024 · Proposed COD May 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

614.4 MW

Capacity

1

Components

Battery

1y 11m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 5m

Facilities Study50%
Queue EntryDec 6, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-07

Queue history
27INR0365 · 22 monthly ERCOT reports, Dec 2024 – Sep 2026

Projected COD moved

2 times

Jan 2027 → May 2029

Net change

+28 months

first report to latest

Capacity

614 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 6, 2024
Facilities study approvedFeb 10, 2026
Interconnection agreement signedMar 20, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
May 7, 2029
From queue filing
Developer in saved assessment
ENERGOS BESS
From queue filing
Status at research time
IA Executed
Active in the ERCOT queue. The LBNL 'Facility Study' stage is stale: ERCOT data shows SS and FIS complete and an interconnection agreement dated 2026-03-20, and an SGIA amendment was filed at the Texas PUC in Aug 2026.
Financing
Not recorded

Milestones in this assessment

IA executedMar 20, 2026Latest in this assessment

ERCOT status data lists the interconnection agreement date for Comanche BESS as 2026-03-20.

app.nrgmap.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. app.nrgmap.com/queues/ercot-27inr0365
  2. ercotqueue.com/project/27INR0365
  3. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
  4. cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0365/comanche-bess
  5. infrasure.ai/project/ercot-27inr0365-comanche-bess

Commercial operation date: NRG Map (ERCOT status data as of 2026-09-01) and Cleanview both show a proposed online date of May 2029, which matches LBNL, but they appear to derive from the same ERCOT data and are not independent. Infrasure's older October 2028 date is superseded. No developer press release or financing-backed target was found.

Developer: Every source that names a developer (ERCOT queue trackers, NRG Map, Infrasure) lists ENERGOS BESS. No parent or operating company was identified. A LinkedIn post about a 600 MW Comanche County project from Misae Investments could not be tied to this queue entry.

Status: NRG Map reports an IA date of 2026-03-20 and ercotqueue.com reports 'IA + FIS complete'. A PUC filing shows Amendment No. 3 to the Oncor SGIA for Comanche BESS. The project is still active and not operating, so the 'operational' label on interxdata is disregarded as an unreliable auto-generated claim.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Comanche BESS project is a proposed 614.4 MW battery storage project located in Comanche County, Texas. The developer is ENERGOS BESS. It is currently in the ERCOT interconnection queue as entry ERCOT-27INR0365, with a queue entry date of December 6, 2024, and a proposed commercial operation date of October 11, 2028. The project's interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 614.4 MW of battery storage capacity. It is interconnected at the #1440 Comanche Switching Station 345kV. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Comanche

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

ENERGOS BESS

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#1440 Comanche Switching Station 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Comanche

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.