Saddle Horn Station Solar SLF
174.64 MW hybrid in Comanche, TX · In queue since September 2024 · Proposed COD September 2028
174.64 MW
Capacity
1
Components
Solar
2y 2m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-11
Projected COD moved
2 times
Jun 2027 → Sep 2028
Net change
+15 months
first report to latest
Capacity
175 MW
unchanged in the reports
Latest stage
Facilities study done
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue in Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify parent company or operating entity behind the project LLC.
Status: LBNL shows active status in Facility Study phase. No news coverage found to indicate construction activity, financing, or status changes.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Saddle Horn Station Solar SLF is a proposed solar-plus-battery hybrid development project in Comanche County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Saddle Horn Station LLC and has a total proposed capacity of 174.64 MW. The listed component data assigns the full 174.64 MW to the solar portion and does not give a separate capacity for the battery storage component. The project would connect to the grid at the 1650 COMANCHE_T8 – 290 SHILOHC 138 kV transmission line.
The project entered the ERCOT interconnection queue on September 4, 2024, under queue ID ERCOT-27INR0351. Its interconnection agreement status is listed at the Facility Study stage, and its proposed commercial operation date is September 11, 2028. The project's current queue status is recorded as suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Aug 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Saddle Horn Station LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1650 COMANCHE_T8 - 290 SHILOHC 138 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Saddle Horn Station Solar SLF
Data-driven briefing on Saddle Horn Station Solar SLF — fleet, generation, financial, and news signals.
Station Solar
Data-driven briefing on Station Solar — fleet, generation, financial, and news signals.
ATI
Data-driven briefing on ATI — fleet, generation, financial, and news signals.
Ion Solar (TX)
Data-driven briefing on Ion Solar — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.