Prairie Blossom Storage
122.5 MW storage in Howard, TX · In queue since December 2024 · Proposed COD May 2029
122.5 MW
Capacity
1
Components
Battery
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-08
Projected COD moved
2 times
Jul 2027 → May 2029
Net change
+22 months
first report to latest
Capacity
120 → 123 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or research sources found to validate or contradict this date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company distinct from the project LLC.
Status: LBNL shows active queue status in Facility Study phase as of December 2024. No news coverage found to provide additional ground-truth status updates.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Prairie Blossom Storage is a proposed 122.5 MW battery storage project located in Howard County, Texas. Developed by Prairie Blossom Storage, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0323, with a queue entry date of December 19, 2024. The proposed commercial operation date is September 21, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The project consists entirely of battery storage, with a total capacity of 122.5 MW. The point of interconnection is the 1322 Big Spring 138kV location. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Prairie Blossom Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1322 Big Spring 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FLCNS_UNIT1
- POI Substation
- Big Spring Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.