Old Victory Energy Center (ERCOT-27INR0253) — Project Summary

Queue ID
ERCOT-27INR0253
Capacity
202.5 MW
Technology
Battery
Status
active
Location
Maverick, TX
Region
ERCOT
Developer
Nova Clean Energy LLC
IA Status
Facility Study

Old Victory Energy Center

ERCOT-27INR0253BetaActiveBatteryERCOTLBNL + Live

202.5 MW storage in Maverick, TX · In queue since May 2024 · Proposed COD June 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

202.5 MW

Capacity

1

Components

Battery

2y 6m

In Queue

Facility Study

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 1m

Facilities Study50%
Queue EntryMay 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-06-01

Queue history
27INR0253 · 30 monthly ERCOT reports, Apr 2024 – Sep 2026

Projected COD moved

1 time

May 2027 → Jun 2030

Net change

+37 months

first report to latest

Capacity

209 → 203 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 9, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
May 1, 2027
Differs from queue: Jun 1, 2030From queue filing
Developer in saved assessment
Nova Clean Energy
From queue filing
Status at research time
Active
Active — Facility Study stage in ERCOT queue, no public construction or financing announcements found
Financing
Not recorded

Milestones in this assessment

IA executedMay 9, 2024Latest in this assessment

Entered ERCOT interconnection queue at Facility Study stage

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of May 2027. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL lists 'Nova Clean Energy LLC' as developer. No news coverage found to identify whether this is a project-specific LLC or the operating parent entity. Treating as single entity absent contradictory evidence.

Status: LBNL status is 'active' at Facility Study stage. No news coverage found to indicate construction start, financing close, or project withdrawal.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Old Victory Energy Center is a proposed 208.8 MW battery storage project located in Maverick County, Texas. Developed by Nova Clean Energy LLC, the project entered the ERCOT interconnection queue as ERCOT-27INR0253 on May 9, 2024. The current proposed commercial operation date is May 1, 2027, and the project's interconnection status is currently in the Facility Study phase.

The proposed project consists entirely of battery storage. The Old Victory Energy Center has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Maverick

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Nova Clean Energy LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

8692 MAVERICK4A 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.