Briefing on Old Victory Energy Center

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
203 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-05-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Old Victory Energy Center is a 203 MW Battery project in Texas, currently active.

Nova Clean Energy LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-05-01.

Queue ID
ERCOT-27INR0253
Location
Maverick, Texas
Technology
Battery
Developer
Nova Clean Energy LLC
Market / region
ERCOT
Point of interconnection
8692 MAVERICK4A 138kV

What stands out

1

Old Victory Energy Center is a 203 MW Battery project in Texas with status active.

2

Nova Clean Energy LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-05-01.

Market and operating context

Queue date
2024-05-09
Proposed COD
2027-05-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Old Victory Energy Center — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0253
LocationMaverick, Texas
TechnologyBattery
DeveloperNova Clean Energy LLC
Market / regionERCOT
Point of interconnection8692 MAVERICK4A 138kV
Queue date2024-05-09
Proposed COD2027-05-01