Easy Wind Energy Center
241.13 MW generation in Schleicher, TX · In queue since May 2024 · Proposed COD December 2027
241.13 MW
Capacity
1
Components
Wind
2 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Easy Wind Energy Center is a proposed wind generation project located in Schleicher County, Texas, within the ERCOT region. The project, developed by Easy Wind Energy Center, LLC, has a total capacity of 241.13 MW. It consists entirely of wind generation.
The project entered the ERCOT interconnection queue as ERCOT-27INR0246 on May 20, 2024, with a proposed commercial operation date of December 1, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 345kV #76003 Big Hill - #76005 Schneeman Draw circuit #1. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Schleicher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Easy Wind Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV #76003 Big Hill - #76005 Schneeman Draw circuit #1
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Easy Wind Energy CenterForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.