Atticus Energy Storage
102.98 MW storage in Sutton, TX · In queue since March 2024 · Proposed COD March 2027
102.98 MW
Capacity
1
Components
Battery
2y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Atticus Energy Storage project is a proposed 102.98 MW battery storage project located in Sutton County, Texas. The project is being developed by Atticus Energy Storage and has appeared in recent news coverage. It is interconnected within the ERCOT queue as entry ERCOT-27INR0236, with a queue entry date of March 29, 2024.
The proposed commercial operation date (COD) for the Atticus Energy Storage project is March 1, 2027. The project's interconnection agreement (IA) status is currently in the Facility Study phase. The point of interconnection (POI) is the 6570 Bond Road Substation 69KV.
Generated from interconnection queue and public data sources
State
TX
County
Sutton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Atticus Energy Storage
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6570 Bond Road Substation 69KV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Atticus Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.