Fierce River Solar
895.67 MW hybrid in Starr, TX · In queue since March 2024 · Proposed COD February 2029
895.67 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-22
Projected COD moved
1 time
Dec 2028 → Feb 2029
Net change
+2 months
first report to latest
Capacity
896 MW
unchanged in the reports
Latest stage
Cancelled
last listed Dec 2025
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-27inr0221-fierce-river-solar
- interconnection.fyi/project/ercot-27inr0221
- interconnection.fyi/projects/state/TX
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0221/fierce-river-solar
- interxdata.com/projects/fierce-river-solar-ercot-27inr0221/
Commercial operation date: Only the LBNL/ERCOT queue date (2029-02-22) exists. Aggregators (cleanview 'Expected online 2029', infrasure 'Proposed COD: 2029-02-22', interconnection.fyi 'February 21, 2029') repeat the queue data rather than giving an independent developer target. One infrasure passage cites Dec 6, 2028, which conflicts with its own header.
Developer: Every source names Rio Grande Solar LLC, which is the LBNL filing entity and probably a project shell. No press release or news item identifies a parent or operating company. The sister project Fierce River BESS (27INR0222) lists the same entity.
Status: LBNL and two trackers (infrasure, interxdata) show active, and infrasure's '2y 7m in queue' suggests recent data. Two interconnection.fyi pages show withdrawn, and the discrepancy is unresolved, so Active is kept with low confidence.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Fierce River Solar is a proposed 895.67 MW solar generation project located in Starr County, Texas. The project, developed by Rio Grande Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0221, with a queue entry date of March 22, 2024. The proposed commercial operation date is December 6, 2028. Its interconnection status is currently in the Facility Study phase.
The point of interconnection for Fierce River Solar is Tap 345 kV 80355 Del Sol - 80119 Frontera Ckt 1. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Dec 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rio Grande Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345 kV 80355 Del Sol - 80119 Frontera Ckt 1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Mesa del Sol Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.