Wander Waters BESS (ERCOT-27INR0207) — Project Summary

Queue ID
ERCOT-27INR0207
Capacity
303.5 MW
Technology
Battery
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Wander Waters BESS LLC
IA Status
Facility Study

Wander Waters BESS

ERCOT-27INR0207BetaActiveBatteryERCOTLBNL + Live

303.5 MW storage in Wilbarger, TX · In queue since March 2024 · Proposed COD October 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

303.5 MW

Capacity

1

Components

Battery

2y 8m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 7m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-10-31

Queue history
27INR0207 · 31 monthly ERCOT reports, Mar 2024 – Sep 2026

Projected COD moved

0 times

Oct 2027 → Oct 2027

Net change

0 months

first report to latest

Capacity

304 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024
Facilities study approvedNov 14, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 31, 2027
From queue filing
Developer in saved assessment
Wander Waters BESS LLC
From queue filing
Status at research time
Active
Active in ERCOT queue at Facility Study phase; no IA executed; no construction or financing announcements found (ercotqueue.com lists build-chance of 16%).
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. infrasure.ai/project/ercot-27inr0207-wander-waters-bess
  2. interconnection.fyi/project/ercot-27inr0207
  3. ercotqueue.com/project/27INR0207
  4. ercotqueue.com/developer/wander-waters-bess-llc
  5. app.nrgmap.com/queues/ercot-27inr0207
  6. cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0207/wander-waters-bess

Commercial operation date: No independent post-LBNL signal exists. Aggregator pages (infrasure.ai, interconnection.fyi, cleanview.co) all repeat the queue-derived proposed COD of October 31, 2027 ('Expected online 2027'), so they are not independent confirmation.

Developer: Only the project-LLC name appears across sources (LBNL, ercotqueue.com, interconnection.fyi). No parent or operating company is identified in press releases. The Redeux Energy cleanview link in the results is not tied to this project in any snippet, so it is not used.

Status: LBNL lists status active, and NRG Map shows active as of Sept 2026 and ercotqueue.com shows the project still on file as active. No evidence of withdrawal or construction.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Wander Waters BESS is a proposed 303.5 MW battery storage project located in Wilbarger County, Texas. The project, developed by Wander Waters BESS LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0207, with a queue entry date of March 22, 2024. The proposed commercial operation date is October 31, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 61001 JIMTREEC7A 345kV substation. Recent news coverage has discussed the development.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wilbarger

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Wander Waters BESS LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

61001 JIMTREEC7A 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.