UNICORN BESS (ERCOT-27INR0142) — Project Summary

Queue ID
ERCOT-27INR0142
Capacity
278.98 MW
Technology
Battery
Status
active
Location
Fort Bend, TX
Region
ERCOT
Developer
Unicorn Energies
IA Status
Facility Study

UNICORN BESS

ERCOT-27INR0142BetaActiveBatteryERCOTLBNL + Live

278.98 MW storage in Fort Bend, TX · In queue since January 2024 · Proposed COD September 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

278.98 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 8m

Facilities Study50%
Queue EntryJan 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-01

Queue history
27INR0142 · 33 monthly ERCOT reports, Jan 2024 – Sep 2026

Projected COD moved

0 times

Sep 2027 → Sep 2027

Net change

0 months

first report to latest

Capacity

279 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 11, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 5y 2m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achievedENR · 2021-09-27

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 1, 2027
From queue filing
Developer in saved assessment
Unicorn Energies
From queue filing
Status at research time
Active
Active — in Facility Study phase per ERCOT queue, no public construction timeline announced
Financing
Not recorded

Milestones in this assessment

IA executedJan 11, 2024

Entered ERCOT interconnection queue

COD targetSep 2027Latest in this assessment

Proposed commercial operation date per ERCOT filing

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of September 2027. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL lists 'Unicorn Energies' as developer. No news coverage found to identify whether this is an operating company or project LLC, or to reveal any parent entity.

Status: LBNL status shows 'active' with IA status at Facility Study stage. No news coverage found to provide ground-truth updates on permitting, financing, or construction progress.

Project lifecycle
as of 2021-09-27
PhaseOnlineENR · 2021-09-27
OperationalYesENR · 2021-09-27
TechnologyBatteryENR · 2021-09-27
DeveloperThe AES Corp.ENR · 2021-09-27
EPC contractorPNG BuildersENR · 2021-09-27
COD achievedReportedENR · 2021-09-27

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Unicorn BESS project is a proposed 278.98 MW battery storage project located in Fort Bend County, Texas. Developed by Unicorn Energies, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0142, with a queue entry date of January 11, 2024, and a proposed commercial operation date of September 1, 2027. The project's interconnection status is currently in the Facility Study phase.

The point of interconnection is the Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP. The Unicorn BESS project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Fort Bend

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Unicorn Energies

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP

Data Source

LBNL + Live

DeveloperThe AES Corp.ENR · 2021-09-27
EPC contractorPNG BuildersENR · 2021-09-27
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.