Query
UNICORN BESS
Type
Entity Briefing
Entity
UNICORN BESS
State
TN
Technology
battery
Generated
2026-10-19T09:44:33.531Z

Briefing on UNICORN BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
279 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-09-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

UNICORN BESS is a 279 MW Battery project in Texas, currently active.

Unicorn Energies is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-09-01.

Queue ID
ERCOT-27INR0142
Location
Fort Bend, Texas
Technology
Battery
Developer
Unicorn Energies
Market / region
ERCOT
Point of interconnection
Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP

What stands out

1

UNICORN BESS is a 279 MW Battery project in Texas with status active.

2

Unicorn Energies is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-09-01.

4

Latest linked story: “Project of the Year: Battery Storage Highlights A First-of-Its-Kind Building” (ENR, 2021-09-27).

Market and operating context

Queue date
2024-01-11
Proposed COD
2027-09-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

UNICORN BESS — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0142
LocationFort Bend, Texas
TechnologyBattery
DeveloperUnicorn Energies
Market / regionERCOT
Point of interconnectionTap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNP
Queue date2024-01-11
Proposed COD2027-09-01