Malachite Solar (ERCOT-27INR0111) — Project Summary

Queue ID
ERCOT-27INR0111
Capacity
184.55 MW
Technology
Solar+Battery
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Malachite Solar LLC
IA Status
Facility Study

Malachite Solar

ERCOT-27INR0111BetaActiveSolarBatteryERCOTLBNL + Live

184.55 MW hybrid in Wharton, TX · In queue since February 2024 · Proposed COD April 2032

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

184.55 MW

Capacity

1

Components

Solar

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2032

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

8y 2m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2032-04-30

Queue history
27INR0111 · 33 monthly ERCOT reports, Jan 2024 – Sep 2026

Projected COD moved

2 times

Jul 2028 → Apr 2032

Net change

+45 months

first report to latest

Capacity

185 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024
Facilities study approvedNov 4, 2025
Interconnection agreement signedDec 26, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2032
From queue filing
Developer in saved assessment
Malachite Solar LLC
From queue filing
Status at research time
Active
Active — early-stage Facility Study phase, no public announcements on development progress
Financing
Not recorded

Milestones in this assessment

IA executedFeb 2024Latest in this assessment

Entered ERCOT interconnection queue, Facility Study phase

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available showing proposed COD of April 2032. No independent news or press releases found to validate or contradict this timeline.

Developer: Only LBNL filing entity 'Malachite Solar LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.

Status: LBNL shows Active status in Facility Study phase. Queue entry from Feb 2024 indicates very early interconnection process with no public development milestones announced.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Malachite Solar is a proposed 184.55 MW solar generation project located in Wharton County, Texas. The project, developed by Malachite Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0111, with a queue entry date of February 27, 2024. The proposed commercial operation date is April 30, 2032.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is identified as The 345 kV Hillje (#44200) _x0013_ Holman (#9073) Line; AEN.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Malachite Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

The 345 kV Hillje (#44200) – Holman (#9073) Line; AEN.

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.