Briefing/projectactive
Malachite Solar is a 185 MW Solar+Battery project in Texas, currently active.
Malachite Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2032-04-30.
- Queue ID
- ERCOT-27INR0111
- Location
- Wharton, Texas
- Technology
- Solar+Battery
- Developer
- Malachite Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- The 345 kV Hillje (#44200) – Holman (#9073) Line; AEN.
What stands out
1
Malachite Solar is a 185 MW Solar+Battery project in Texas with status active.
2
Malachite Solar LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2032-04-30.
Market and operating context
- Queue date
- 2024-02-27
- Proposed COD
- 2032-04-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.