Antonio Road BESS
155.52 MW storage in Bastrop, TX · In queue since October 2023 · Proposed COD June 2027
155.52 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
Projected COD moved
1 time
May 2026 → Jun 2027
Net change
+13 months
first report to latest
Capacity
156 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Jul 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue application submitted to ERCOT, assigned ID 27INR0090
cleanview.coResearch sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0090/antonio-road-bess
- cleanview.co/planned-battery-projects/TX/27INR0090/antonio-road-bess
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-7d3
Commercial operation date: LBNL queue snapshot shows June 2027 COD. Cleanview aggregator confirms same date (May 2027 in one instance, June 2027 in another). No independent press releases or developer announcements found to validate or contradict this target.
Developer: Only source is LBNL filing entity 'Tempus Power management LLC'. No press releases, corporate announcements, or news coverage found identifying parent company or confirming this is an operating entity vs. project SPV.
Status: LBNL status is 'active' at Facility Study stage. No news coverage of groundbreaking, financing, or permitting milestones found. Project appears to be in early interconnection-study phase.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Antonio Road BESS project is a proposed 155.52 MW battery storage project located in Bastrop County, Texas. Developed by Tempus Power Management LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0090, with a queue entry date of October 13, 2023. The proposed commercial operation date is June 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is the Paige 138kV bus number 7308, connecting to the existing substation via the addition of a breaker. The Antonio Road BESS project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Bastrop
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tempus Power management LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Paige 138kV, bus 7308, connecting to the existing substation via adding a breaker
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Paige Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.