Darkwood BESS
150.5 MW generation in Comanche, TX · In queue since June 2023 · Proposed COD July 2028
150.5 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Projected COD moved
2 times
Jan 2027 → Jul 2028
Net change
+18 months
first report to latest
Capacity
151 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Comanche County document lists completion date 01/30/2027 for Darkwood BESS
bloximages.newyork1.vip.townnews.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1636489723727376/
- bloximages.newyork1.vip.townnews.com/thecomanchechief.com/content/tncms/assets/v3/editorial/d/23/d23c6420-675b-4875-94e0-a6f72b7eca85/6802814d32c41.pdf.pdf
- ercotqueue.com/project/27INR0050
- ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
Commercial operation date: LBNL queue shows 2028-07-01, but a local PDF document from Comanche County explicitly states completion date 01/30/2027 for Darkwood BESS, approximately 1.5 years earlier than the queue filing.
Developer: LBNL filing uses project LLC 'Mustang Creek Solar, LLC', but Facebook community post explicitly identifies the parent structure: 'Mustang Solar LLC for Core Solar, parent company TotalEnergies.'
Status: LBNL status 'active' confirmed by multiple sources. Ercotqueue.com shows IA + FIS complete with 86% build probability. ERCOT MORA May 2026 lists project targeting 2028 North zone.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Darkwood BESS project is a proposed 150.5 MW battery storage project located in Comanche County, Texas. It is being developed by Mustang Creek Solar, LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0050, with a queue entry date of June 7, 2023, and a proposed commercial operation date of September 20, 2027. The project's interconnection agreement status is currently in the Facility Study phase.
Recent news coverage has discussed the Darkwood BESS development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mustang Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345KV 1900 Comanche Peak - 1440 Comanche Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Proctor Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.