Sunscape Renewable Energy Solar SLF
522.75 MW hybrid in Nueces, TX · In queue since June 2023 · Proposed COD October 2028
522.75 MW
Capacity
1
Components
Solar
3y 5m
In Queue
IA Executed
IA Phase
Signed Jul 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
4y 3m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-10-31
Projected COD moved
4 times
Jul 2027 → Oct 2028
Net change
+15 months
first report to latest
Capacity
523 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed for the 345 kV POI at the Lon C Hill to Reforzar line.
infrasure.aiResearch sources and reasoning (6 recorded sources)
low confidence at research time
- sunscaperenewableenergy.com/
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0047/sunscape-renewable-energy-solar-slf
- infrasure.ai/project/ercot-27inr0047-sunscape-renewable-energy-solar-slf
- interconnection.fyi/project/ercot-27inr0047
- ercotqueue.com/project/27INR0047
- app.nrgmap.com/queues/ercot-27inr0047
Commercial operation date: No press release, news item or developer statement gives a COD. The aggregators (interconnection.fyi "proposed completion date is October 31, 2028", Cleanview "Expected online 2028") appear to mirror the queue data, so they are not independent confirmation. Infrasure is internally inconsistent (June 2028 vs. January 2029), so the LBNL date stands.
Developer: The LBNL filing entity, Sunscape Renewable Energy LLC, matches the operating brand on sunscaperenewableenergy.com, and every tracker lists the same developer. The Vesper Energy Development LLC mention on interconnection.fyi comes from an EIA-860 'matched facility' and is not tied to this project, so I did not treat it as an ownership signal.
Status: LBNL shows active with an executed IA, and Infrasure and ercotqueue.com agree. The interxdata 'operational' label contradicts LBNL (is_operational false) and every other source, so I treated it as erroneous.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Sunscape Renewable Energy Solar SLF is a proposed 522.75 MW solar generation project located in Nueces County, Texas. The project, developed by Sunscape Renewable Energy LLC, is interconnected within the ERCOT region under queue ID ERCOT-27INR0047. It entered the interconnection queue on June 28, 2023, with a proposed commercial operation date of January 26, 2029.
The project's Interconnection Agreement (IA) has been executed as of July 18, 2024. The point of interconnection is the Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sunscape Renewable Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- C
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.