Hovey Solar 2
7.5 MW generation in — · In queue since November 2025 · Proposed COD July 2026
7.5 MW
Capacity
1
Components
Solar
1 year
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8 months
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-18
Projected COD moved
1 time
Jul 2026 → Sep 2026
Net change
+2 months
first report to latest
Capacity
8 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Hovey Solar 2 is a proposed 7.5 MW solar generation project in the Electric Reliability Council of Texas (ERCOT) region. The developer is Barilla Solar, LLC. The project consists of a single solar component with a capacity of 7.5 MW. It is designed to interconnect to the grid at the Solstice 138 kV point of interconnection (bus 60385). The provided data does not specify the county in which the project is located.
The project is listed in the ERCOT interconnection queue under queue ID ERCOT-26INR0736 and holds an active status. It entered the queue on November 28, 2025, and has a proposed commercial operation date of July 18, 2026. Its interconnection agreement status is recorded as in progress, though the specific study phase is not identified in the queue data.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Aug 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BARILLA SOLAR, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60385 Solstice 138 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HOVEY_GEN
- POI Substation
- Solstice Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.