Bexar Martinez BESS
9.99 MW storage in — · In queue since September 2025 · Proposed COD August 2026
9.99 MW
Capacity
1
Components
Battery
1y 2m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
11 months
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-05
Projected COD moved
2 times
Nov 2026 → Jan 2027
Net change
+2 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Energized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bexar Martinez BESS (queue ID ERCOT-26INR0702) is a proposed battery energy storage development project with a total capacity of 9.99 MW, located within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Bexar Martinez LLC and consists of a single battery storage component rated at 9.99 MW. Its point of interconnection is the Martinez transmission service provider station (station code C5), where it would connect at the 138 kV transmission level via load transformer T3 at PTI bus number 5294.
The project entered the ERCOT interconnection queue on September 14, 2025, and its status is listed as active. Its interconnection agreement status is recorded as in progress, though the specific study phase is not identified. The proposed commercial operation date is August 5, 2026, less than a year after the project's queue entry.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
—
County
—
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bexar Martinez LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TSP Station Name: Martinez_x000D_ TSP Station Code: C5_x000D_ Load Name / Load Transformer Name: T3_x000D_ Bus #: PTI Bus Number: 5294_x000D_ Voltage (Transmission level kV): 138_x000D_ Node (associated w/ load/load XFMR in NMMS): C5349100111-F
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.