Aquila Solar
500 MW generation in Milam, TX · In queue since November 2025 · Proposed COD November 2026
500 MW
Capacity
1
Components
Solar
1 year
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1 year
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-12
Projected COD moved
0 times
Nov 2026 → Nov 2026
Net change
0 months
first report to latest
Capacity
500 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-26inr0635-aquila-solar
- interconnection.fyi/project/ercot-26inr0635
- cleanview.co/power-projects/planned/solar-farms/texas/26INR0635/aquila-solar
Commercial operation date: Only the LBNL/ERCOT filing gives a proposed COD of 2026-11-12. The aggregator sites (infrasure.ai, interconnection.fyi, cleanview) repeat the same queue data and are not independent. No press release or news confirms a financing-backed target. A November 2026 COD is also aggressive for a project that entered the queue in November 2025 at Facility Study stage.
Developer: Only the LBNL filing entity 'Ben Milam Solar 5' appears, and the aggregators just repeat it. No parent or operating company was identified in any source. The name looks like a project LLC, but its parent can't be determined from the evidence.
Status: LBNL lists the project as active with a Facility Study IA status and no IA date. The interxdata snippet calling it 'operational' contradicts LBNL (is_operational=false) and the queue stage, so it was disregarded. No news indicates withdrawal or construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Aquila Solar project is a proposed 500 MW solar photovoltaic generation facility in Milam County, Texas. Developed by Ben Milam Solar 5, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0635, with a queue entry date of November 18, 2025. The proposed commercial operation date is November 12, 2026.
The project will interconnect at the 3706 Gibson Switch 345kV point of interconnection.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ben Milam Solar 5
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3706 Gibson Switch 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.