Betel Storage II
500 MW storage in Milam, TX · In queue since January 2025 · Proposed COD December 2026
500 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-17
Projected COD moved
0 times
Dec 2026 → Dec 2026
Net change
0 months
first report to latest
Capacity
500 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-26inr0633
- ercotqueue.com/project/26INR0633
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0633/betel-storage-ii
- ercotqueue.com/developer/betel-storage-ii
- infrasure.ai/project/ercot-26inr0633-betel-storage-ii
Commercial operation date: No news or press-release source gives a developer-backed COD for this project. Only queue aggregators (cleanview 'Expected online 2026', interconnection.fyi 'December 17, 2026') repeat the LBNL/ERCOT date. The project has no IA and is at the Facility Study stage, so the date is likely optimistic.
Developer: Every source lists the developer as 'BETEL STORAGE II', which is the project-name shell entity. No press release or article identifies a parent or operating company.
Status: LBNL and the ERCOT trackers (interconnection.fyi, ercotqueue.com) all show the project as active. One aggregator (interxdata) says 'operational', which contradicts the others and the lack of any IA, so I discounted it.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Betel Storage II project is a proposed 500 MW hybrid battery energy storage project located in Milam County, Texas. The project, developed by BETEL STORAGE II, is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It entered the ERCOT interconnection queue as queue ID ERCOT-26INR0633 on January 28, 2025, with a proposed commercial operation date of December 17, 2026.
The Betel Storage II project is listed as an active project in the interconnection queue. Recent news coverage indicates industry interest in the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BETEL STORAGE II
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3377 Little Pond 345
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.