Juno 3 Solar (ERCOT-26INR0621) — Project Summary

Queue ID
ERCOT-26INR0621
Capacity
500 MW
Technology
Solar
Status
active
Location
Borden, TX
Region
ERCOT
Developer
Juno Solar 3
IA Status
IA Executed

Juno 3 Solar

ERCOT-26INR0621BetaActiveSolarERCOTLBNL + Live

500 MW generation in Borden, TX · In queue since March 2025 · Proposed COD November 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

500 MW

Capacity

1

Components

Solar

1y 8m

In Queue

IA Executed

IA Phase

Signed Jul 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4 months

IA → COD

2y 4m

Total Duration

4 months

Construction75%
Queue EntryMar 24, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 1, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-11-30

Queue history
26INR0621 · 19 monthly ERCOT reports, Mar 2025 – Sep 2026

Projected COD moved

0 times

Nov 2027 → Nov 2027

Net change

0 months

first report to latest

Capacity

500 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 24, 2025
Interconnection agreement signedJul 1, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

News-reported activity
as of 5y 2m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achievedpv magazine USA · 2021-09-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Nov 30, 2027
From queue filing
Developer in saved assessment
SB Energy
Filed as Juno Solar 3
Status at research time
IA Executed
Active in the ERCOT queue with IA executed 2025-07-01; no public evidence of groundbreaking, permitting or construction start. The operating Juno Solar (418 MW, COD 2021) is a separate, earlier phase.
Financing
Not recorded

Milestones in this assessment

IA executedJul 1, 2025Latest in this assessment

Interconnection agreement executed for Juno 3 Solar (500 MW, Borden County, TX), per the LBNL/ERCOT queue record.

interconnection.fyi
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-26inr0621
  2. cleanview.co/power-projects/planned/solar-farms/texas/26INR0621/juno-3-solar
  3. sbenergy.com/project/juno/
  4. pv-magazine-usa.com/2021/09/01/watch-juno-solar-enters-service-in-texas-with-418-mw-of-capacity/

Commercial operation date: Only the LBNL/ERCOT queue record gives a date (proposed COD 2027-11-30). Cleanview's 'Expected online 2027' and interconnection.fyi's 'proposed completion date is November 30, 2027' appear to be mirrors of that record, not independent signals. No developer press release or news article about Juno 3 specifically was found.

Developer: The LBNL filing entity 'Juno Solar 3' follows the naming of SB Energy's operating 418 MW Juno Solar project in the same county (Borden, TX; sbenergy.com/project/juno). This is an inference: no source names SB Energy as developer of Juno 3 directly, and the news-extracted developer facts describe Juno Solar and the Orion cluster.

Status: The LBNL record shows an active queue entry with an executed IA and is_operational=false. The 2021 'COD achieved' news refers to the original Juno Solar, not Juno 3, so it does not change this status.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Juno 3 Solar project is a proposed 500 MW solar photovoltaic generation project located in Borden County, Texas. Developed by Juno Solar 3, the project is in the ERCOT interconnection queue as entry ERCOT-26INR0621, with a queue entry date of March 24, 2025. An Interconnection Agreement (IA) was executed on July 1, 2025, and the proposed commercial operation date is November 30, 2027. The point of interconnection is #59916 Buck Canyon 345kV.

The Juno 3 Solar project has been the subject of recent news coverage, with five articles categorized as industry news and deal announcements.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Borden

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Juno Solar 3

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#59916 Buck Canyon 345kV

Data Source

LBNL + Live

DeveloperSB EnergyPV Tech · 2024-10-21
EPC contractorSignal Energypv magazine USA · 2021-09-01
TransactionPPAPV Tech · 2024-10-21
OfftakerGoogle±PV Tech · 2024-10-21
PPA structurePhysicalPV Tech · 2024-10-21
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (4)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.