Bonham Storage SLF (ERCOT-26INR0619) — Project Summary

Queue ID
ERCOT-26INR0619
Capacity
104.92 MW
Technology
Solar+Battery
Status
active
Location
Limestone, TX
Region
ERCOT
Developer
J&J Solar Ranch LLC
IA Status
Facility Study

Bonham Storage SLF

ERCOT-26INR0619BetaActiveBatteryBatteryERCOTLBNL + Live

104.92 MW generation in Limestone, TX · In queue since January 2025 · Proposed COD July 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

104.92 MW

Capacity

1

Components

Battery

1y 10m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 6m

Facilities Study50%
Queue EntryJan 28, 2025

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Queue history
26INR0619 · 21 monthly ERCOT reports, Jan 2025 – Sep 2026

Projected COD moved

2 times

Aug 2026 → Jul 2027

Net change

+11 months

first report to latest

Capacity

104 → 105 MW

changed in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 28, 2025
Facilities study approvedSep 17, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 1, 2027
From queue filing
Developer in saved assessment
J&J Solar Ranch LLC
From queue filing
Status at research time
Active
Active — Facility Study stage in ERCOT queue as of January 2025, no public construction or financing announcements
Financing
Not recorded

Milestones in this assessment

IA executedJan 28, 2025Latest in this assessment

Entered ERCOT queue at Facility Study stage

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of July 2027. No independent news or press releases found to validate or contradict this target date.

Developer: Only LBNL filing identifies developer as J&J Solar Ranch LLC. No public news, corporate website, or press releases found to identify a parent operating company or confirm this is a project-specific LLC.

Status: LBNL status shows Active with Facility Study in progress. No news coverage or milestones found to indicate progression beyond interconnection study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Bonham Storage SLF project is a proposed 104.92 MW hybrid battery energy storage project located in Limestone County, Texas. Developed by J&J Solar Ranch LLC, the project consists of battery storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0619, with a queue entry date of January 28, 2025, and a proposed commercial operation date of April 5, 2027.

The point of interconnection for the project is Tap 138kV 3632 Mexia_Main - 3634 Groesbeck_Main.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Limestone

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

J&J Solar Ranch LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 3632 Mexia_Main - 3634 Groesbeck_Main

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.