Scorpius Solar
600 MW generation in Milam, TX · In queue since December 2024 · Proposed COD June 2029
600 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-14
Projected COD moved
2 times
Oct 2026 → Jun 2029
Net change
+32 months
first report to latest
Capacity
500 → 600 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-26inr0609-scorpius-solar
- interconnection.fyi/project/ercot-26inr0609
- cleanview.co/power-projects/planned/solar-farms/texas/26INR0609/scorpius-solar
- ercotqueue.com/project/26INR0609
- app.nrgmap.com/queues/ercot-26inr0609
- groundtrace.io/developers/ben-milam-solar-4-7ednickaa2df2
Commercial operation date: Every source that gives a COD (cleanview, infrasure.ai, interconnection.fyi) repeats the LBNL/ERCOT proposed date of June 2029. These are queue-data aggregators, not independent developer signals, so there is no post-LBNL evidence of a different date.
Developer: All sources name Ben Milam Solar 4 as developer, and they appear to derive this from the ERCOT queue. No press release or parent company was found, so the actual operating company can't be identified.
Status: LBNL shows active, and NRG Map confirms active as of Sept 2026. Groundtrace says none of the developer's projects is under construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Scorpius Solar project is a proposed 500 MW solar generation facility located in Milam County, Texas. The project, developed by Ben Milam Solar 4, is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0609, with a queue entry date of December 16, 2024. The proposed commercial operation date is June 14, 2029, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 500 MW of solar photovoltaic generation. It is planned to interconnect at the 3377 LTPSW 345KV point of interconnection. The Scorpius Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Milam
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Ben Milam Solar 4
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
3377 LTPSW 345KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.