Crocus Storage
51 MW hybrid in Stephens, TX · In queue since January 2025 · Proposed COD July 2028
51 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Crocus Storage project is a proposed 51 MW hybrid battery energy storage project located in Stephens County, Texas. Developed by Crocus Solar, LLC, the project entered the ERCOT interconnection queue as entry ERCOT-26INR0601 on January 28, 2025. The current proposed commercial operation date is July 1, 2028.
The project is listed as active in the interconnection queue. The point of interconnection is Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613).
Generated from interconnection queue and public data sources
State
TX
County
Stephens
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Crocus Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)
Data Source
Live · ERCOT
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Crocus StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.