Query
Crocus Storage
Type
Entity Briefing
Entity
Crocus Storage
Generated
2026-10-19T16:30:39.056Z

Briefing on Crocus Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
51 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-07-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Crocus Storage is a 51 MW Solar+Battery project in Texas, currently active.

Crocus Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-07-01.

Queue ID
ERCOT-26INR0601
Location
Stephens, Texas
Technology
Solar+Battery
Developer
Crocus Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)

What stands out

1

Crocus Storage is a 51 MW Solar+Battery project in Texas with status active.

2

Crocus Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-07-01.

Market and operating context

Queue date
2025-01-28
Proposed COD
2028-07-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Crocus Storage — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0601
LocationStephens, Texas
TechnologySolar+Battery
DeveloperCrocus Solar, LLC
Market / regionERCOT
Point of interconnectionTap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613)
Queue date2025-01-28
Proposed COD2028-07-01