Cairos Storage 2
184 MW storage in Kinney, TX · In queue since July 2024 · Proposed COD December 2026
184 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
Projected COD moved
2 times
Mar 2026 → Dec 2028
Net change
+33 months
first report to latest
Capacity
184 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Jul 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Cleanview reports expected online date of December 2026
cleanview.coResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/planned-battery-projects/TX/26INR0448/cairos-storage-2
- interconnection.fyi/projects/state/TX/kinney-county
- renewablesinfo.org/browse/projects/texas
- interconnection.fyi/projects/state/TX
Commercial operation date: Cleanview.co (Result 7) reports 'expected online December 2026', which is 2 years earlier than LBNL's 2028-12-31 filing. Cleanview aggregates queue data with updated timelines, suggesting the LBNL date is stale.
Developer: No alternative developer names found in search results. 'Cairos Solar, LLC' appears to be the operating entity, not a shell LLC. No ownership changes or parent company references discovered.
Status: LBNL reports 'active' status in Facility Study phase. No news of construction start, financing, or withdrawal found in search results.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cairos Storage 2 is a proposed 184 MW battery storage project located in Kinney County, Texas. The project, developed by Cairos Solar, LLC, is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-26INR0448 on July 1, 2024. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of December 31, 2026.
The development project consists entirely of battery storage, with a total capacity of 184 MW. The point of interconnection is the 7425 ODLAW SWITCH 138kV. The project is currently listed as active in the ERCOT interconnection queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Kinney
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Cairos Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7425 ODLAW SWITCH 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.