Cairos Storage 2 (ERCOT-26INR0448) — Project Summary

Queue ID
ERCOT-26INR0448
Capacity
184 MW
Technology
Battery
Status
active
Location
Kinney, TX
Region
ERCOT
Developer
Cairos Solar, LLC
IA Status
Facility Study

Cairos Storage 2

ERCOT-26INR0448BetaActiveBatteryERCOTLBNL

184 MW storage in Kinney, TX · In queue since July 2024 · Proposed COD December 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

184 MW

Capacity

1

Components

Battery

2y 4m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 5m

Facilities Study50%
Queue EntryJul 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Queue history
26INR0448 · 26 monthly ERCOT reports, Jun 2024 – Jul 2026

Projected COD moved

2 times

Mar 2026 → Dec 2028

Net change

+33 months

first report to latest

Capacity

184 MW

unchanged in the reports

Latest stage

Cancelled

last listed Jul 2026

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJul 1, 2024
CancelledAug 24, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Jul 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 2026
Developer in saved assessment
Cairos Solar, LLC
From queue filing
Status at research time
Active
Active — Facility Study phase per LBNL, no construction announcements yet
Financing
Not recorded

Milestones in this assessment

COD targetDec 2026Latest in this assessment

Cleanview reports expected online date of December 2026

cleanview.co
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. cleanview.co/planned-battery-projects/TX/26INR0448/cairos-storage-2
  2. interconnection.fyi/projects/state/TX/kinney-county
  3. renewablesinfo.org/browse/projects/texas
  4. interconnection.fyi/projects/state/TX

Commercial operation date: Cleanview.co (Result 7) reports 'expected online December 2026', which is 2 years earlier than LBNL's 2028-12-31 filing. Cleanview aggregates queue data with updated timelines, suggesting the LBNL date is stale.

Developer: No alternative developer names found in search results. 'Cairos Solar, LLC' appears to be the operating entity, not a shell LLC. No ownership changes or parent company references discovered.

Status: LBNL reports 'active' status in Facility Study phase. No news of construction start, financing, or withdrawal found in search results.

About

Saved background

Generated Apr 10, 2026 · Predates Jul 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Cairos Storage 2 is a proposed 184 MW battery storage project located in Kinney County, Texas. The project, developed by Cairos Solar, LLC, is interconnected within the ERCOT region and entered the interconnection queue as ERCOT-26INR0448 on July 1, 2024. The current interconnection status is listed as Facility Study, with a proposed commercial operation date of December 31, 2026.

The development project consists entirely of battery storage, with a total capacity of 184 MW. The point of interconnection is the 7425 ODLAW SWITCH 138kV. The project is currently listed as active in the ERCOT interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • LBNL queue source as of: Dec 31, 2025.
  • Queue history observations through: Jul 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Kinney

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Cairos Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

7425 ODLAW SWITCH 138kV

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.