Big Rooter West Solar (ERCOT-26INR0431) — Project Summary

Queue ID
ERCOT-26INR0431
Capacity
403.42 MW
Technology
Solar+Battery
Status
active
Location
Robertson, TX
Region
ERCOT
Developer
Big Rooter West, LLC
IA Status
IA Executed

Big Rooter West Solar

ERCOT-26INR0431BetaActiveSolarBatteryERCOTLBNL + Live

403.42 MW hybrid in Robertson, TX · In queue since March 2024 · Proposed COD May 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

403.42 MW

Capacity

1

Components

Solar

2y 8m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

11 months

IA → COD

3y 3m

Total Duration

11 months

Construction75%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 18, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-05-31

Queue history
26INR0431 · 31 monthly ERCOT reports, Mar 2024 – Sep 2026

Projected COD moved

3 times

Dec 2026 → May 2028

Net change

+17 months

first report to latest

Capacity

403 → 403 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024
Facilities study approvedDec 5, 2024
Interconnection agreement signedFeb 18, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
2028
Developer in saved assessment
Panamint Capital
Filed as Big Rooter West, LLC
Status at research time
Construction
LBNL shows Active with IA executed (Feb 2025). Panamint broke ground on Big Rooter West (phase 1, 491 MWdc) in July 2026, and phase 2 (Big Rooter East) is slated to start construction in December 2026.
Financing
Not recorded

Milestones in this assessment

IA executedFeb 2025

Interconnection agreement signed Feb 2025, consistent with the LBNL snapshot (IA date 2025-02-18).

infrasure.ai
GroundbreakingJul 24, 2026

Panamint Capital broke ground on the $1.7B Big Rooter Power project. Phase 1 (Big Rooter West, 491 MWdc) is under construction.

texaspolitics.com
COD targetAug 2028Latest in this assessment

Commercial operations for Big Rooter West are targeted for August 2028. Phase 2 (Big Rooter East) is targeted for August 2029.

texaspolitics.com
Research sources and reasoning (4 recorded sources)

high confidence at research time

  1. texaspolitics.com/2026/07/24/panamint-breaks-ground-on-1-7-billion-texas-solar-project-at-former-coal-site/
  2. panamintcapital.com/portfolio/redevelopment/
  3. kbtx.com/2026/07/30/massive-17b-solar-project-breaks-ground-robertson-county/
  4. infrasure.ai/project/ercot-26inr0431-big-rooter-west-solar

Commercial operation date: Panamint's groundbreaking coverage says Big Rooter West (phase 1) is under construction with commercial operations expected in August 2028. That is about 3 months after the LBNL date of 2028-05-31, and Panamint's portfolio page also says 2028. Only the year is stated as consensus because no day is given.

Developer: The LBNL filer 'Big Rooter West, LLC' is a project LLC. Panamint Capital announced groundbreaking on Big Rooter Power, whose first phase is named 'Big Rooter West', at its Twin Oaks site in Robertson County. The shared project name and location link the LLC to Panamint, but no source states the ownership link explicitly.

Status: The July 2026 Panamint announcement and KBTX coverage report that construction on the first phase has begun. This moves the project past the LBNL queue status of Active.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Big Rooter West Solar SLF is a proposed solar generation project located in Robertson County, Texas, with a total capacity of 403.42 MW. Developed by Big Rooter West, LLC, the project consists entirely of solar photovoltaic generation.

The project is currently in the ERCOT interconnection queue as entry ERCOT-26INR0431, with a queue entry date of March 22, 2024. Its proposed commercial operation date is May 31, 2028, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is listed as 39950# TNTNP_ONE_3 345 KV. The project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Robertson

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Big Rooter West, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

39950# TNTNP_ONE_3 345 KV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.