Twinwood Solar 1 (ERCOT-26INR0425) — Project Summary

Queue ID
ERCOT-26INR0425
Capacity
358.06 MW
Technology
Solar
Status
active
Location
Waller, TX
Region
ERCOT
Developer
Twinwood PV1, LLC
IA Status
Facility Study

Twinwood Solar 1

ERCOT-26INR0425BetaActiveSolarERCOTLBNL + Live

358.06 MW generation in Waller, TX · In queue since March 2024 · Proposed COD February 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

358.06 MW

Capacity

1

Components

Solar

2y 8m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 11m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-02-01

Queue history
26INR0425 · 26 monthly ERCOT reports, Aug 2024 – Sep 2026

Projected COD moved

2 times

May 2027 → Feb 2029

Net change

+21 months

first report to latest

Capacity

383 → 358 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024
Interconnection agreement signedNov 7, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Oct 27, 2027
Differs from queue: Feb 1, 2029
Developer in saved assessment
Twinwood PV1, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage. No interconnection agreement is executed and no construction or financing news was found.
Financing
Not recorded
Research sources and reasoning (6 recorded sources)

low confidence at research time

  1. infrasure.ai/project/ercot-26inr0425-twinwood-solar-1
  2. cleanview.co/power-projects/planned/solar-farms/texas/26INR0425/twinwood-solar-1
  3. interconnection.fyi/project/ercot-26inr0425
  4. ercotqueue.com/project/26INR0425
  5. app.nrgmap.com/queues/ercot-26inr0425
  6. ercotqueue.com/developer/twinwood-pv1-llc

Commercial operation date: Infrasure lists 'Proposed COD: 2027-10-27' and Cleanview says 'Expected online 2027', both later than the LBNL date of 2029-02-01. Both are queue aggregators rather than developer announcements, and interconnection.fyi still shows 2029-02-01, so the evidence is thin.

Developer: Every source names Twinwood PV1, LLC, which looks like a project shell. No press release or news item identifies a parent or operating company. The Waller County Elin Energy articles are about an unrelated panel factory.

Status: Infrasure, interconnection.fyi, ercotqueue.com and NRG Map all show the project as active, with the Facility Study and IA pending. One aggregator (interxdata) says 'operational', which contradicts the others and the queue data, so I treated it as an error.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Twinwood Solar 1 is a proposed solar generation project located in Waller County, Texas, within the ERCOT region. The project, developed by Twinwood PV1, LLC, has a total capacity of 358.06 MW. It consists entirely of solar photovoltaic generation.

The project is listed in the ERCOT interconnection queue as entry ERCOT-26INR0425, with a queue entry date of March 22, 2024. The proposed commercial operation date is October 27, 2027. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Waller

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Twinwood PV1, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 44750 FULSHR_S25_8 - 44860 TWINWD_S25_8

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.