Whitetail BESS
180 MW storage in Mitchell, TX · In queue since February 2024 · Proposed COD June 2029
180 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-08
Projected COD moved
3 times
Dec 2026 → Jun 2029
Net change
+30 months
first report to latest
Capacity
180 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Project entered ERCOT queue as 26INR0420
cleanview.coResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0420/whitetail-bess
- ercotqueue.com/project/26INR0420
- ercotqueue.com/developer/hunt-energy-network-llc
- images1.showcase.com/d2/-0De-RO-jQonkpQ2jP1NIhlV4X4KhA7CUOhUCTtJjTw/document.pdf
Commercial operation date: Only source for COD is the LBNL queue snapshot showing June 2029. No press releases, financing announcements, or developer statements found to validate or update this date.
Developer: Hunt Energy Network, LLC appears consistently across all sources as both the filing entity and operating company. No evidence of shell-LLC structure or parent company differentiation found.
Status: LBNL shows 'active' status at Facility Study stage with no IA date. Third-party queue trackers confirm active status with low build-chance given early interconnection stage.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Whitetail BESS is a proposed 180 MW battery energy storage development project located in Mitchell County, Texas. The project is being developed by Hunt Energy Network, LLC and consists of a single battery storage component with a capacity of 180 MW. It is planned to connect to the grid at the #23846 SALTMN_SU8 138kV point of interconnection.
The project is listed in the Electric Reliability Council of Texas (ERCOT) interconnection queue under queue ID ERCOT-26INR0420. It entered the queue on February 27, 2024, and currently holds an active status. The project is in the Facility Study phase of the interconnection process and has not yet reached an interconnection agreement. Its proposed commercial operation date is June 8, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hunt Energy Network, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#23846 SALTMN_SU8 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.