Liatris Flexible Gas
204.71 MW generation in Brazoria, TX · In queue since March 2024 · Proposed COD February 2029
204.71 MW
Capacity
1
Components
Gas
2y 8m
In Queue
IA Executed
IA Phase
Signed Nov 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 8m
IA → COD
3y 3m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 24–48 months
Proposed COD: 2029-02-01
Projected COD moved
2 times
May 2026 → Feb 2029
Net change
+33 months
first report to latest
Capacity
205 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed between CenterPoint Energy Houston Electric and Stone Creek Peaker LLC
interchange.puc.texas.gov205 MW gas turbine project targeting February 2029 commercial operation in ERCOT Coastal region
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&FilingParty=centerpoint&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
- ercot.com/files/docs/2026/04/02/MORA_June2026.pdf
- ercotqueue.com/project/26INR0408
Commercial operation date: LBNL queue snapshot shows proposed COD of 2029-02-01, confirmed in ERCOT MORA documents (May 2026, April 2026) listing the project with 2029 target. No contradictory news sources found.
Developer: All sources consistently identify Stone Creek Peaker LLC as the developer. No parent company or operating entity identified in search results; appears to be a project-specific entity rather than a shell LLC for a larger developer.
Status: LBNL shows IA Executed status with IA date of 2025-11-01. Texas PUC Interchange filings from November 2025 confirm ERCOT Standard Generation Interconnection Agreement execution between CenterPoint and Stone Creek Peaker LLC.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Liatris Flexible Gas project is a proposed 204.71 MW gas-fired generation project located in Brazoria County, Texas. Developed by Stone Creek Peaker LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0408, with a queue entry date of March 22, 2024.
The proposed commercial operation date for the project is February 1, 2029. Its interconnection status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brazoria
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Stone Creek Peaker LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV (42980) Nash - (44010) WA Parish CKT02
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.