HILLBORO BESS
127.29 MW generation in Hill, TX · In queue since February 2024 · Proposed COD September 2028
127.29 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-21
Projected COD moved
1 time
Dec 2027 → Sep 2028
Net change
+9 months
first report to latest
Capacity
127 → 131 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Queue application submitted to ERCOT, entered Facility Study phase
interconnection.fyiResearch sources and reasoning (2 recorded sources)
low confidence at research time
Commercial operation date: Only LBNL queue filing provides a COD of September 21, 2028. No news or press releases found discussing project timeline or construction schedule.
Developer: Only LBNL filing identifies developer as 'Abei Energy Green XI LLC'. No news coverage or corporate announcements found to confirm parent company or operating entity. The LLC naming pattern suggests a project vehicle, but no parent company information is available.
Status: LBNL shows 'active' status in Facility Study phase. No news coverage of project development, permitting, or construction activity found.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
HILLBORO BESS (queue ID ERCOT-26INR0402) is a proposed energy development project in Hill County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by Abei Energy Green XI LLC, the project has a total proposed capacity of 127.29 MW. The queue classifies its technology as Wind+Battery, but the only component in the project data is a 127.29 MW battery energy storage system, which is consistent with the "BESS" in its name. The project is listed as a generation project.
The project entered the ERCOT interconnection queue on February 27, 2024, and remains active. Its interconnection agreement status is listed as "Facility Study," meaning it is still undergoing interconnection studies and has not yet reached an executed agreement. The proposed point of interconnection is a tap on the 138 kV line between the HILLBORO1_8 (bus 3522) and CHATT (bus 234) substations. The project's proposed commercial operation date is September 21, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Hill
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Abei Energy Green XI LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 138 kV 3522 HILLBORO1_8 - 234 CHATT
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.