Blackcat Storage (ERCOT-26INR0376) — Project Summary

Queue ID
ERCOT-26INR0376
Capacity
200.59 MW
Technology
Battery
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
Matagorda ESS, LLC
IA Status
Facility Study

Blackcat Storage

ERCOT-26INR0376BetaActiveBatteryERCOTLBNL + Live

200.59 MW storage in Matagorda, TX · In queue since January 2024 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.59 MW

Capacity

1

Components

Battery

2y 10m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 11m

Facilities Study50%
Queue EntryJan 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Queue history
26INR0376 · 33 monthly ERCOT reports, Jan 2024 – Sep 2026

Projected COD moved

1 time

Apr 2026 → Dec 2027

Net change

+20 months

first report to latest

Capacity

201 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 11, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 31, 2027
From queue filing
Developer in saved assessment
RIC Energy
Filed as Matagorda ESS, LLC
Status at research time
Active
Active — Facility Study stage, no IA executed yet. ERCOTqueue.com estimates 5% build-chance based on lack of IA progress.
Financing
Not recorded

Milestones in this assessment

COD targetApr 5, 2026

Original proposed COD before being pushed to December 2027

interconnectionfyi.substack.com
COD targetDec 30, 2027Latest in this assessment

Revised proposed completion date per April 2025 queue update

interconnectionfyi.substack.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0376/blackcat-storage
  2. interconnection.fyi/project/ercot-26inr0376
  3. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
  4. cleanview.co/power-projects/developers/ric-energy
  5. ercotqueue.com/project/26INR0376

Commercial operation date: LBNL queue shows proposed COD of 2027-12-31. Interconnection.fyi notes the date changed from April 2026 to December 2027, but no independent press releases or developer announcements confirm a different target. Using LBNL date as consensus.

Developer: LBNL filing entity is 'Matagorda ESS, LLC' (project-specific shell). Cleanview's RIC Energy developer page lists Blackcat Storage as a top pipeline project under RIC Energy, indicating RIC Energy is the operating parent company.

Status: LBNL shows 'active' status at Facility Study stage with no IA date. Multiple tracker sources confirm active queue position with no construction or financing announcements.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Blackcat Storage project is a proposed 200.59 MW battery energy storage system in Matagorda County, Texas. Developed by Matagorda ESS, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0376, with a queue entry date of January 11, 2024. The proposed commercial operation date is December 31, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138kV Blackcat Substation (#80124). The project has appeared in recent news coverage regarding energy storage development in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Matagorda

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Matagorda ESS, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

138kV Blackcat Substation (#80124)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
BAYC_BESS_RN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-04-09

View all articles