Blackcat Storage
200.59 MW storage in Matagorda, TX · In queue since January 2024 · Proposed COD December 2027
200.59 MW
Capacity
1
Components
Battery
2y 10m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Projected COD moved
1 time
Apr 2026 → Dec 2027
Net change
+20 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Original proposed COD before being pushed to December 2027
interconnectionfyi.substack.comRevised proposed completion date per April 2025 queue update
interconnectionfyi.substack.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0376/blackcat-storage
- interconnection.fyi/project/ercot-26inr0376
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-db7
- cleanview.co/power-projects/developers/ric-energy
- ercotqueue.com/project/26INR0376
Commercial operation date: LBNL queue shows proposed COD of 2027-12-31. Interconnection.fyi notes the date changed from April 2026 to December 2027, but no independent press releases or developer announcements confirm a different target. Using LBNL date as consensus.
Developer: LBNL filing entity is 'Matagorda ESS, LLC' (project-specific shell). Cleanview's RIC Energy developer page lists Blackcat Storage as a top pipeline project under RIC Energy, indicating RIC Energy is the operating parent company.
Status: LBNL shows 'active' status at Facility Study stage with no IA date. Multiple tracker sources confirm active queue position with no construction or financing announcements.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Blackcat Storage project is a proposed 200.59 MW battery energy storage system in Matagorda County, Texas. Developed by Matagorda ESS, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0376, with a queue entry date of January 11, 2024. The proposed commercial operation date is December 31, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 138kV Blackcat Substation (#80124). The project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Matagorda ESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV Blackcat Substation (#80124)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BAYC_BESS_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09