Pinnacle Point Energy Storage (ERCOT-26INR0317) — Project Summary

Queue ID
ERCOT-26INR0317
Capacity
101.3 MW
Technology
Battery
Status
active
Location
Harris, TX
Region
ERCOT
Developer
GCI Pinnacle Point, LLC
IA Status
Facility Study

Pinnacle Point Energy Storage

ERCOT-26INR0317BetaActiveBatteryERCOTLBNL + Live

101.3 MW storage in Harris, TX · In queue since November 2023 · Proposed COD July 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

101.3 MW

Capacity

1

Components

Battery

3 years

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 8m

Facilities Study50%
Queue EntryNov 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-10

Queue history
26INR0317 · 35 monthly ERCOT reports, Nov 2023 – Sep 2026

Projected COD moved

2 times

Jun 2026 → Jul 2029

Net change

+37 months

first report to latest

Capacity

101 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 14, 2023
Facilities study approvedNov 10, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jun 1, 2027
Differs from queue: Jul 10, 2029From queue filing
Developer in saved assessment
GCI Pinnacle Point, LLC
From queue filing
Status at research time
Active
Active in ERCOT queue at Facility Study stage — no public evidence of construction activity, financing, or permitting progress
Financing
Not recorded

Milestones in this assessment

IA executedNov 2023Latest in this assessment

Entered ERCOT queue in Facility Study stage, no IA executed

interconnection.fyi
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0317/pinnacle-point-energy-storage
  2. interconnection.fyi/project/ercot-26inr0317
  3. ercotqueue.com/project/26INR0317
  4. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx

Commercial operation date: LBNL queue snapshot shows June 2027 COD. No press releases, financing announcements, or developer communications found to validate or update this target. Third-party aggregators (Cleanview, ercotqueue.com) echo the LBNL date without independent confirmation.

Developer: Only source is LBNL filing entity 'GCI Pinnacle Point, LLC'. No press releases, corporate websites, or news coverage identify a parent company or operating entity. The LLC name pattern suggests a project SPV, but no parent can be confirmed from available sources.

Status: LBNL shows 'active' status in Facility Study phase (no IA executed). Zero news coverage, press releases, or financing announcements found. Project appears to be in early interconnection process with no visible commercial momentum.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Pinnacle Point Energy Storage is a proposed 101.3 MW battery storage project located in Harris County, Texas. The project, developed by GCI Pinnacle Point, LLC, is currently in the ERCOT interconnection queue as entry ERCOT-26INR0317, with a queue entry date of November 14, 2023. The proposed commercial operation date is June 1, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.

The Pinnacle Point Energy Storage project has been the subject of recent news coverage, with four articles appearing in categories such as regulatory, deals, and industry news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Harris

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

GCI Pinnacle Point, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap Highlands (Bus # 40812) - HANEY ( BUS # 40790) 138 kV

Data Source

LBNL + Live

TransactionProject financingUtility Dive · 2025-01-09
Deal value$1.8BUtility Dive · 2025-01-09
LenderU.S. Department of Energy Loan Programs OfficeUtility Dive · 2025-01-09
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26