Whitewright Solar 2
301.69 MW generation in Grayson, TX · In queue since December 2023 · Proposed COD May 2028
301.69 MW
Capacity
1
Components
Solar
2y 11m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-02
Projected COD moved
3 times
Oct 2026 → May 2028
Net change
+19 months
first report to latest
Capacity
300 → 302 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- infrasure.ai/project/ercot-26inr0300-whitewright-solar-2
- interconnection.fyi/project/ercot-26inr0300
- ercotqueue.com/project/26INR0300
- app.nrgmap.com/queues/ercot-26inr0300
Commercial operation date: The only COD signal is the LBNL/ERCOT proposed COD of 2028-05-02. The aggregator sites (infrasure, interconnection.fyi) repeat the same queue data, not an independent developer target. The 2021-06 'COD achieved' news fact describes the Coniglio Solar Project, a different, already-built project, so it was not applied.
Developer: Every current source, including ERCOT-derived trackers, names SunWR, LLC. The Q CELLS developer fact is tied to the completed Coniglio project (2021), and nothing links it to this queue entry, so no parent or ownership change is asserted.
Status: LBNL, ercotqueue.com and NRG Map all show the entry as active with no IA. The interxdata 'operational' label conflicts with all other sources and with the Facility Study stage, so it was treated as an error.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Whitewright Solar 2 is a proposed 301.69 MW solar generation project located in Grayson County, Texas. The project, being developed by SunWR, LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0300, with a queue entry date of December 18, 2023. Its proposed commercial operation date is May 2, 2028, and its interconnection agreement status is currently in the Facility Study phase.
The proposed project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grayson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SunWR, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 1729 Valley South – Anna Switch 2373
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.