Hill Valley BESS (ERCOT-26INR0285) — Project Summary

Queue ID
ERCOT-26INR0285
Capacity
245.8 MW
Technology
Battery
Status
active
Location
Grimes, TX
Region
ERCOT
Developer
Hill Valley BESS, LLC
IA Status
Facility Study

Hill Valley BESS

ERCOT-26INR0285BetaActiveBatteryERCOTLBNL + Live

245.8 MW storage in Grimes, TX · In queue since December 2023 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

245.8 MW

Capacity

1

Components

Battery

2y 11m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 7m

Facilities Study50%
Queue EntryDec 4, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-15

Queue history
26INR0285 · 35 monthly ERCOT reports, Nov 2023 – Sep 2026

Projected COD moved

2 times

Jan 2026 → Jul 2028

Net change

+30 months

first report to latest

Capacity

205 → 246 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedDec 4, 2023
Facilities study approvedDec 3, 2024
Interconnection agreement signedApr 21, 2026

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 2028
From queue filing
Developer in saved assessment
Hill Valley BESS, LLC
From queue filing
Status at research time
Active
Active — Facility Study phase, no construction or financing announcements yet
Financing
Not recorded

Milestones in this assessment

IA executed

Project in Facility Study phase, IA not yet executed

cleanview.co
COD targetJul 2028Latest in this assessment

Expected commercial operation July 2028

cleanview.co
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0285/hill-valley-bess
  2. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
  3. interconnection.fyi/project/ercot-26inr0285
  4. interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending

Commercial operation date: LBNL queue snapshot shows proposed COD of 2028-07-15. Cleanview aggregator confirms 'expected to come online in July 2028.' No contradictory signals from news or developer announcements.

Developer: Only source is LBNL filing entity 'Hill Valley BESS, LLC.' No press releases, corporate announcements, or news coverage identifying a parent operating company. Texas PUC filings confirm the LLC as the legal entity but provide no parent company information.

Status: LBNL shows 'active' status in Facility Study phase (no IA executed). No news coverage of project milestones, permitting, or financing. Cleanview and Interconnection.fyi aggregators confirm active queue status but no ground activity.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Hill Valley BESS project is a proposed 245.8 MW battery storage project located in Grimes County, Texas. Developed by Hill Valley BESS, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-26INR0285, with a queue entry date of December 4, 2023. The proposed commercial operation date is July 15, 2028.

The project's interconnection status is currently in the Facility Study phase. The Point of Interconnection (POI) is the 345 kV Singleton substation (#44645). The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Grimes

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Hill Valley BESS, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

345 kV Singleton (#44645)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.