Bonaparte BESS
153.67 MW storage in Lee, TX · In queue since November 2023 · Proposed COD December 2027
153.67 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-29
Projected COD moved
1 time
Aug 2026 → Dec 2027
Net change
+16 months
first report to latest
Capacity
154 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jan 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Lee County Commissioners' Court held public hearing on designating Reinvestment Zone for Bonaparte BESS project
co.lee.tx.usProject withdrawn from ERCOT queue in February 2026 cancellation cycle
facebook.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- renewablesinfo.org/project/ercot-26inr0283-bonaparte-bess
- co.lee.tx.us/upload/page/5438/docs/Comm%20Court/Notice%20of%20Public%20Hearing%20August%2012%202024.pdf
- interconnection.fyi/projects/state/TX
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1850559615653718/
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1659858264723855/
Commercial operation date: Only LBNL queue data provides a COD target of 2027-12-29. No press releases or news articles with updated COD targets were found in search results.
Developer: All sources reference only 'Bonaparte BESS, LLC' as the developer. No parent company or operating entity identified in available sources. This appears to be a project-specific LLC with no public disclosure of ultimate ownership.
Status: While LBNL snapshot shows 'active' status from November 2023, multiple independent Facebook posts from community tracking groups (June 2025, December 2025) explicitly list 'Bonaparte BESS - Lee - 02/20/2026 - 153.67' under ERCOT cancellations. interconnection.fyi also lists status as 'Withdrawn'.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Bonaparte BESS project is a proposed 153.67 MW battery storage project located in Lee County, Texas. Developed by Bonaparte BESS, LLC, the project consists entirely of battery storage. It is currently in the ERCOT interconnection queue as entry ERCOT-26INR0283, with a queue entry date of November 14, 2023. The proposed commercial operation date is August 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The project would interconnect at the 7568 Lincoln 138 kV point of interconnection. Recent news coverage has discussed the development project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jan 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Lee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Bonaparte BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
7568 Lincoln 138 kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Lincoln Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.