Salt-Lick Solar
453 MW hybrid in Culberson, TX · In queue since October 2023 · Proposed COD June 2028
453 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Projected COD moved
2 times
Dec 2026 → Jun 2028
Net change
+18 months
first report to latest
Capacity
510 → 453 MW
changed in the reports
Latest stage
Cancelled
last listed Jul 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/26INR0277/salt-lick-solar
- interconnection.fyi/project/ercot-26inr0277
- infrasure.ai/project/ercot-26inr0277-salt-lick-solar
- ercotqueue.com/developer/salt-lick-solar-llc
Commercial operation date: The LBNL proposed COD is 2028-06-01. Cleanview ('Expected online 2028') and Infrasure ('proposed commercial operation date is June 1, 2028') repeat the same date, but both look derived from the queue data, so there is no independent developer or press-release target.
Developer: No press release or news names an operating parent. An Infrasure line says the project 'entered ERCOT queue as Salt Lick Solar Park LLC under EDPR ownership'. It is a single aggregator claim with no date or supporting source, and the same page gives 510 MW instead of 453 MW, so I did not treat it as a confirmed parent or ownership change.
Status: LBNL, Infrasure and ercotqueue.com (1 active, 0 dropped for this developer) all show the project as active. Only interconnection.fyi says withdrawn, and I could not corroborate that, so I kept LBNL's status.
About
Generated Apr 10, 2026 · Predates Jul 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Salt-Lick Solar is a proposed 510 MW solar generation project located in Culberson County, Texas. The project, developed by Salt-Lick Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0277, with a queue entry date of October 13, 2023. The proposed commercial operation date is June 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Salt-Lick Solar development has been the subject of recent news coverage, with three articles focusing on deals related to the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jul 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Culberson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Salt-Lick Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Elcor_8 bus # 11198
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.