Salt-Lick Solar
453 MW hybrid in Culberson, TX · In queue since October 2023 · Proposed COD June 2028
453 MW
Capacity
1
Components
Solar
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Project entered ERCOT queue as Salt Lick Solar Park LLC under EDPR ownership
sourceSalt-Lick Solar is a proposed 510 MW solar generation project located in Culberson County, Texas. The project, developed by Salt-Lick Solar, LLC, is in the ERCOT interconnection queue as entry ERCOT-26INR0277, with a queue entry date of October 13, 2023. The proposed commercial operation date is June 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The Salt-Lick Solar development has been the subject of recent news coverage, with three articles focusing on deals related to the project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Culberson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Salt-Lick Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Elcor_8 bus # 11198
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.