Momentum Stout BESS
125.5 MW storage in Burnet, TX · In queue since November 2023 · Proposed COD October 2027
125.5 MW
Capacity
1
Components
Battery
3 years
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-01
Projected COD moved
1 time
Apr 2026 → Oct 2027
Net change
+18 months
first report to latest
Capacity
126 MW
unchanged in the reports
Latest stage
Cancelled
last listed May 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue as 26INR0272, currently in Facility Study phase
cleanview.coResearch sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0272/momentum-stout-bess
- interconnection.fyi/project/ercot-26inr0272
- ercotqueue.com/project/26INR0272
- renewablesinfo.org/project/ercot-26inr0272-momentum-stout-bess
Commercial operation date: LBNL queue filing shows October 2027 COD. No independent news sources provide alternative dates; third-party aggregators (Cleanview, interconnection.fyi) echo the LBNL filing without additional sourcing.
Developer: All sources consistently identify 'Momentum STOUT, LLC' as the developer. No press releases, parent company disclosures, or ownership changes found. Entity appears to be the operating company rather than a shell LLC.
Status: LBNL status is 'active' with IA status at 'Facility Study' stage. No news coverage indicates project advancement beyond interconnection studies.
About
Generated Apr 10, 2026 · Predates May 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Momentum Stout BESS project is a proposed 125.5 MW battery storage project located in Burnet County, Texas. Developed by Momentum STOUT, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0272, with a queue entry date of November 14, 2023. The proposed commercial operation date is October 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 70111 Flat Rock 138kV. The Momentum Stout BESS project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: May 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Burnet
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Momentum STOUT, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
70111 Flat Rock 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Flat Rock Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.